Cabinets go in before countertops. Always. Every time. There is no version of a kitchen where the stone shows up first.
The reason is worth understanding, because it explains most of the rest of the kitchen sequence too: your countertop is templated to the cabinets as they were actually installed, not as they were drawn. Walls aren't straight. Floors aren't level. A cabinet run drawn at 96 inches gets built into a wall that's out of square, and shims and scribes bring it in true. The fabricator measures reality. The drawing is a proposal; the installed cabinets are the fact.
Once you accept that, the rest of the sequence falls into place. Here's the whole thing, and why each step is where it is.
The Sequence
- 1Demo. Old cabinets, counters, and backsplash out.
- 2Framing, electrical, and plumbing rough changes. Anything moving inside the walls happens now, while they're open: under-cabinet lighting, new circuits, relocated sink drain and supply, the hood duct.
- 3Inspection, if the scope triggers one.
- 4Drywall and patch. Close the walls back up and make them flat.
- 5Prime and paint the walls -- mostly. Roll them now, before the room is full of cabinetry to work around. Save a touch-up coat for the end.
- 6Flooring decision point. Under the cabinets, or up to them. See below; this gets decided here and it has consequences.
- 7Set and LEVEL the cabinet boxes. Shim, scribe, fasten to studs, join box to box. Everything else depends on this step.
- 8Template the countertops. The fabricator measures the installed boxes.
- 9Fabrication lead time. A real dead stretch. Nothing happens on site.
- 10Countertop install.
- 11Plumbing hookup. Faucet, disposal, dishwasher -- none of it connects until the stone is set.
- 12Backsplash tile, after the counter, so it lands on the counter.
- 13Doors, drawer fronts, hardware, toe kick, crown, final paint touch-up.
Level Is Not Optional
Setting cabinets level is the least glamorous step in a kitchen and the one that determines whether the expensive part survives. Stone is rigid and brittle. It does not bend to follow an uneven cabinet run. If the boxes are out of level, the slab bridges the high spots and hangs unsupported over the low ones -- point loading. Lean on it, set a heavy pot down near a seam, and it cracks. Cracked stone isn't repairable in any way you'll be happy with. It's a replacement slab and a replacement bill.
So the crew shims. Every box, in both directions, fastened to studs and joined face frame to face frame so the run behaves as one piece. Time spent leveling cabinets is insurance on the countertop.
What the Fabricator Needs On Site
Templating is either digital -- a laser rig that builds a precise model of the space -- or physical, with strips of material assembled into a pattern of the counter. Either way, the fabricator isn't just measuring the perimeter. They're locating cutouts.
- The sink on site, or at minimum the exact make and model confirmed. Undermount sinks are cut and polished to the specific bowl.
- A farmhouse / apron-front sink must be physically installed before templating. It sits in a modified cabinet box and the stone is cut to land on it. There is no templating around a farmhouse sink that isn't there yet.
- The cooktop -- exact model, so the cutout matches the appliance and not a similar one.
- The faucet and any soap dispenser or air switch, so the holes land in the right places.
- Overhang decisions -- how far the counter extends past the island cabinets for seating, and whether that overhang needs brackets or corbels underneath. Settle it at template, not after.
Show up to template day with a box of "we'll figure it out later" and you'll either delay the template or get a slab with a hole in the wrong place.
The Dead Week After Template
After template, the slab goes to the shop to be cut, edged, and polished. That takes real time, and it varies with the material and the shop's queue. Meanwhile your kitchen has cabinets, no counters, no working sink, and nobody on site. This is not a stall. It's the fabrication window, it's on the schedule from day one, and your temporary kitchen needs to survive it.
Why Backsplash Comes After the Counter
The backsplash sits on the countertop, because the counter is the reference plane the bottom course lands on and gets caulked to. Tile the wall first and you'll be trying to slide a slab under finished tile -- the joint will be a mess, or the slab simply won't fit. Counter first, then tile down to it, then a soft joint of caulk rather than grout where tile meets stone, because the two move at different rates and a rigid joint there will crack.
The Flooring Debate: Under the Cabinets, or Up to Them
This is a legitimate fork in the road and both answers are defensible. What isn't defensible is failing to decide on purpose.
Flooring wall-to-wall, under the cabinets
The floor goes across the entire room, then cabinets sit on top of it. It costs more material, because you're paying for flooring nobody will ever see. What that money buys: a future where you can change the layout, swap the cabinet configuration, or pull an appliance out without discovering a hole in your floor. Everything sits at a consistent height. It's the flexible answer and it ages well.
Flooring up to the cabinets
Cabinets go first and the flooring is cut in around them. Less material, less waste -- and with an expensive floor, that adds up. The trade-off is that the layout is now locked. Change a cabinet run later and you've got bare subfloor where a cabinet used to be, and matching that flooring years on is its own adventure.
The same trap catches slide-in ranges and under-counter refrigeration. Any appliance that lives in a cabinet opening has to be able to come back out of it. Check that on paper first.
A Few Things People Get Backward
- Drill the doors off the box. Hardware gets bored on a bench with a jig, not on a hung door where a slip gouges a finished cabinet.
- Toe kick goes on near the end. It's a finish piece and every trade in the room scuffs it.
- Final paint touch-up is genuinely last -- after the punch list, not before.
- Appliances get staged, not installed early. A new range sitting in an active job site is a range that gets scratched.
Want Someone Who Sequences It Right the First Time?
Order of operations never shows up in the finished photos and shows up in every single thing that goes wrong. Getting it right is craft, not luck. If you're remodeling a kitchen in Newnan, Sharpsburg, or anywhere across Coweta County and you want a crew that knows why the stone waits on the cabinets and why the dishwasher has to be able to come out, reach Wright Way Services at (770) 301-4638. We'll walk your kitchen and lay out the sequence before you spend a dollar.